Reclamation work consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, and spot replacement of curbs.

Notify Us

Click on Notify Us above to tell us about anything on your property or street related to the current projects.

Contacts

Links

Updates

Click on your street segment on the map below or see below for updates.

September 13, 2019

Paving the first layers of asphalt on the east side of River Hills Drive West from Highway 13 to Raleigh Drive has been postponed to the week of September 16, 2019 due to weather. Replacement of the pavement on the west side is scheduled to begin September 23, 2019.

September 3, 2019

The east side of River Hills Drive West from Highway 13 to Raleigh Drive is scheduled for paving the week of September 9, 2019. Grinding up of the asphalt on the west side will take place shortly afterwards. Grading and paving on the west side is tentatively scheduled to be complete around early October 2019.