Burnsville Heights Area

Subscribe to email updates

Overview

The Burnsville Heights Area is planned for a 2018 street reconstruction project. This street reconstruction project consists of complete curb and gutter replacement, roadway reconstruction, water main replacement, storm sewer repairs and upgrades, and sanitary sewer repairs.

Contacts

Project Manager: Assistant City Engineer Email John Schmeling

Project Inspector: Engineering Technician Email Cody Pietz

Links

Updates

June 3, 2019

The contractor will be repairing concrete curb and driveways on or around Tuesday June 4, 2019. 

Please note that the contractor's sod maintenance period ends June 9, 2019.  Please contact project inspector Cody Pietz at 952-356-6839 or cody.pietz@burnsvillemn.gov if you have any questions or concerns about sod in your boulevard.   Please refer to the Sod Installation Letter in the "Links" section of the page for more information on sod maintenance.

April 24, 2019

The contractor is planning to start grading boulevards on or around Thursday 4/25/19.  Sod installation is scheduled to start on or around the middle of the week of 4/29/19.

December 17, 2018

The contractor placed straw mulch in the areas that have not been sodded.  This mulch is temporary cover to reduce erosion in the spring prior to sod being placed.  The straw mulch will be removed prior to sodding in the spring.